Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 23103MF2VT01
Vendor/Entity Legal Name (if applicable): Sander Engineering Corporation
MWDBE Contracted Goal (if applicable): 19.6%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Sander Engineering Corporation in the amount of $198,249.00 for Professional Engineering Services in connection with Wastewater System Rehabilitation - Spring Camp and Klein Park - 2022, UPIN 23103MF2VT01, Precinct 3, MWDBE Contracted Goal: 19.6%.
end
Background and Discussion:
The wastewater from Spring Camp and Klein Park is currently pumped to an existing On-Site Sewage Facility. Sander Engineering Corporation is tasked with providing design, bid, and construction phase services for the design and construction of a lift station and force main to eliminate the On-Site Sewage Facility and send the wastewater to Bridgestone Municipal Utility District.
Expected Impact:
This project will reduce maintenance costs for the Precinct as well as prevent potential environmental hazards caused by an aging On-Site Sewage Facility.
Alternative Options:
If the agreement is not approved, the Precinct may decide to not move forward with the project and will continue to incur increased maintenance costs. If the project moves forward and is designed in-house, Harris County Engineering Department would have to increase staffing to perform and execute the work, which could cause delays.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
X Public Health
_ Transportation
_ Flooding
X Environment
_ Governance and Customer Service
Prior Court Action (if any):