Harris County Logo
File #: 24-2398    Version: 1 Name:
Type: Contract - Award Status: Agenda Ready
File created: 4/12/2024 In control: Commissioners Court
On agenda: 4/23/2024 Final action:
Title: Request for approval of an award on the basis of low bid to Reytec Construction Resources, Inc. in the amount of $8,222,205 for drainage improvements in the Aldine Village and Oak Glen Place Subdivisions - (2018) West Package for Precinct 2 and for the County Clerk to execute any applicable bonds to be received (240016), MWDBE Contracted Goal: 18%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 240016
Vendor/Entity Legal Name (if applicable): Reytec Construction Resources, Inc.

MWDBE Contracted Goal (if applicable): 18%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to Reytec Construction Resources, Inc. in the amount of $8,222,205 for drainage improvements in the Aldine Village and Oak Glen Place Subdivisions - (2018) West Package for Precinct 2 and for the County Clerk to execute any applicable bonds to be received (240016), MWDBE Contracted Goal: 18%.
end

Background and Discussion:
The Aldine Village Subdivision Drainage Improvements - 2018 (West Package) project consists of subdivision drainage improvements Major work activities include constructing a new storm sewer system and reconstructing roadside ditches along Lillja Road, including culvert and driveway replacements, between Connorvale Lane and a point approximately 400' south of Walston Lane. New storm sewer inlets will be constructed on Connorvale Lane, Corvette Lane, and Walston Lane.

The Oak Glen Place Subdivision Drainage Improvements West Package project site consists of subdivision drainage improvements and stormwater detention basin located on Lilja Road between Aldine Mail Route Road and Charriton Street, in north Harris County; discharging into HCFCD Channel P118-00-00. Major
work activities include approximately 4,670 linear feet of reinforced concrete storm sewer consisting of various reinforced concrete pipe sizes, reinforced concrete box sizes, inlets, manholes, junction boxes, culvert headwall/wingwall structures and removal and reconstruction of existing driveways. The stormwater detention basin construction...

Click here for full text