Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 23050MF2QJ01
Vendor/Entity Legal Name (if applicable): Civitas Engineering Group Inc
MWDBE Contracted Goal (if applicable): 19.6%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Civitas Engineering Group Inc in the amount of $463,359.00 for Professional Engineering Services in connection with Destination Trail Segment 1B - Brays Bayou at Scott Street, UPIN 23050MF2QJ01, Precinct 1, MWDBE Contracted Goal: 19.6%.
end
Background and Discussion:
Professional Services needed to design trail undercrossing along Brays Bayou at Scott Street and mid-block crossing improvement.
Expected Impact:
Provide enhanced mobility for pedestrian access along Brays Bayou Trails.
Alternative Options:
No alternative options. Project will be delayed or cancelled.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
12/05/23
56
Request for approval to negotiate
Location:
Address (if applicable): Scott St at Brays Bayou
Precinct(s): Precinct 1
Fiscal and Personnel Summary
Service Name
Engineering
Current Fiscal Year Cost
Annual Fiscal Cost
Labor
Non-Labor
Total
Recurring Expenses
Funding Sources
Existing Budget
1070 - Mobility Fund
$
$463,359.00
$463,359.00
$
Choose an item.
$
$
$
$
Choose an item.
$
$
$
$
Total Current Budget
$
$463,359.00
$463,359.00
$
Additional Budget Request (Requires Fiscal Review Request Form)
Choose an item.
$
$
$
$
Choose an item.
$
$
$
$
Choose an item.
$
...
Click here for full text