File #: 24-2262    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 4/10/2024 In control: Commissioners Court
On agenda: 4/23/2024 Final action:
Title: Request for approval of change in contract No. 6 with Lecon, Inc., for Major Maintenance of Cypress Creek and Tributaries Batch 3, adding 30 calendar days with no change to the contract amount. (Cypress Creek Watershed, Bond ID CI-012, Project ID K100-00-00-X087, Job No. 22/0085, Precincts 1 and 3, MWDBE Contracted Goal: 20.5%, MWDBE Current Participation: 24.30%).
Attachments: 1. 042324 CIC LECON K100-X087 PCT 1 AND 3 backup.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): K100-00-00-X087
Vendor/Entity Legal Name (if applicable): Lecon, Inc.

MWDBE Contracted Goal (if applicable): 20.5%
MWDBE Current Participation (if applicable): 24.30%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 6 with Lecon, Inc., for Major Maintenance of Cypress Creek and Tributaries Batch 3, adding 30 calendar days with no change to the contract amount. (Cypress Creek Watershed, Bond ID CI-012, Project ID K100-00-00-X087, Job No. 22/0085, Precincts 1 and 3, MWDBE Contracted Goal: 20.5%, MWDBE Current Participation: 24.30%).
end

Background and Discussion:
This project is Batch 3 of Maintenance Protects on Cypress Creek and its Tributaries; this batch covers twelve (12) sites and construction is approximately 82% complete and expected to be completed by mid-2024.
The purpose of this change order is to reconcile pay items across eight (8) project sites to address changes in field conditions, and to extend the time of completion due to inclement weather.

Expected Impact:
This change will allow for additional days to complete the project to realize flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than canceling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.


Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
05/10/2022
213.
Award
01/10/...

Click here for full text