File #: 24-2218    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 4/10/2024 In control: Commissioners Court
On agenda: 4/23/2024 Final action:
Title: Request for approval of a change in contract with Serco Construction Group, Ltd. in connection with Cedar Bayou Park East and West Subdivision Drainage Improvements - 2018, adding seven calendar days with an addition in the amount of $78,115.70, Job No. 23/0042-1, UPIN 19102MF15W01, Precinct 2, MWDBE Contracted Goal: 100%, MWDBE Current Participation: 100%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19102MF15W01 - Job. No.: 23/0042
Vendor/Entity Legal Name (if applicable): Serco Construction Group, Ltd

MWDBE Contracted Goal (if applicable): 100%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Serco Construction Group, Ltd. in connection with Cedar Bayou Park East and West Subdivision Drainage Improvements - 2018, adding seven calendar days with an addition in the amount of $78,115.70, Job No. 23/0042-1, UPIN 19102MF15W01, Precinct 2, MWDBE Contracted Goal: 100%, MWDBE Current Participation: 100%.
end

Background and Discussion:
The Cedar Bayou Park East and West Subdivision Drainage Improvements project site consists of subdivision drainage improvements and a stormwater detention basin located south of IH 10 from Sjolander Road to Bayou Boulevard, in east Harris County, discharging into HCFCD Channels Q113-00-00 and Q114-00-00. Major work activities include approximately 25,300 linear feet of reinforced concrete storm sewer consisting of various reinforced concrete pipe sizes, reinforced concrete box sizes, inlets, manholes, junction boxes, culvert headwall/wing wall structures, removal and reconstruction of existing driveways, and proposed detention pond.

The Change in contract request includes new items for the following:
* PCO-1. Adding additional days to the contract is needed for the contractor's additional effort of coordination with the constituents for the on-site operation during clearing and grubbing with an additional $0.00 and 2 days.
* PCO-3. Adding new line items is needed for the Concrete Collar and Coring of RCB to connect th...

Click here for full text