Title: Request for approval of an amendment to an agreement with LJA Engineering, Inc., in the amount of $300,000, to provide additional engineering services in support of the Brays Bayou Federal Flood Control Project on HCFCD Unit D100-00-00. (Brays Bayou Watershed, Project ID D100-00-00-G005, Agreement No. 2020-61, Countywide, MWDBE Contracted Goal: 19%).
Attachments: 1. 042324 AGMT LJA 2020-61 CW 2020-61 CW backup.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): D100-00-00-G005
Vendor/Entity Legal Name (if applicable): LJA Engineering, Inc.

MWDBE Contracted Goal (if applicable): 19%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with LJA Engineering, Inc., in the amount of $300,000, to provide additional engineering services in support of the Brays Bayou Federal Flood Control Project on HCFCD Unit D100-00-00. (Brays Bayou Watershed, Project ID D100-00-00-G005, Agreement No. 2020-61, Countywide, MWDBE Contracted Goal: 19%).
end

Background and Discussion:
The purpose of this amendment is to complete the Design Documentation Report (DDR) related to Project Brays from D100-00-00-G005. Since this is for Engineering Services, there is no specific prioritization framework score or quartile under the 2022 Prioritization Framework approved by Commissioners Court.

Expected Impact:
This amendment is needed to produce documentation for the Flood Control District to be reimbursed by the US Army Corps of Engineers for funds spent by the Flood Control District for engineering and construction of Project Brays.

Alternative Options:
The alternative to this agreement being approved is that we will need additional in-house personnel to support the work to be performed, which will cause significant interruption and delays in reimbursements.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
08/24/2000
1.a.1
ATN
7/30/2019
2.a.10
Agreement

Locati...

Click here for full text