Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 20/0099, UPIN 21104M23F502
Vendor/Entity Legal Name (if applicable): Professional Traffic Control, LLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Professional Traffic Control LLC, in connection with final construction of On-Call - Maintenance - Thermoplastic Striping-2020, with an addition in the amount of $17,237.45, Job No. 20/0099-1, UPIN 21104M23F502, Precinct 4.
end
Background and Discussion:
This project consists of a renewable thermoplastic striping (Type I material) contract for various roads in Precinct 4. The work includes but is not limited to thermoplastic striping, pavement markings, raised reflectorized markers, shoulder blading, and traffic control. The work also includes the pavement markings for adjacent intersections with major thoroughfare roads.
The overrun is due to Precinct 4 request for additional of roads to be marked for the safety of the users and residents of Harris County.
Quantity to be added:
Item #9 Reflectorized pavement markings type I (thermoplastic) 4" white/solid - furnish & applied:
22037 LF x $.75/LF = $16,527.75
Item #12 Reflectorized pavement markings type I (thermoplastic) 8" white/solid - furnish & applied:
473.13 LF x $1.50 = $709.70
Total Amount = $16,527.75 + $709.70 = $17,237.45
PCO #3 FINAL ADJUSTMENTS - $17,237.45 - 0 days (HCNTY-0000058966)
Expected Impact:
Change allows to have funds available so contractor can be compensated for their mowing activities completed within Katy Zone, Precinct 4.
Alternative Options:
There are no alternative ...