Title: Request for approval of a change in contract with Conrad Construction Co., LTD in connection with final WCID #50 Drainage Improvements-2020, with a deduction in the amount of $262,838.03, Job No. 21/0195-13, UPIN 21102MF1WF01, Precinct 2, MWDBE Contracted Goal: 9.00%, MWDBE Current Participation: 9.06%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 21102MF1WF01 - Job No. 21/0195
Vendor/Entity Legal Name (if applicable): Conrad Construction Co., LTD

MWDBE Contracted Goal (if applicable): 9.00%
MWDBE Current Participation (if applicable): 9.06%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Conrad Construction Co., LTD in connection with final WCID #50 Drainage Improvements-2020, with a deduction in the amount of $262,838.03, Job No. 21/0195-13, UPIN 21102MF1WF01, Precinct 2, MWDBE Contracted Goal: 9.00%, MWDBE Current Participation: 9.06%.
end

Background and Discussion:
The project is in southeast Harris County within the City of El Lago limits, under the Harris County Water Control and Improvement District 50 (WCID 50) jurisdiction. The project scope consists of the removal and disposal of existing storm sewer and installing storm sewer, waterline, pavement, bulkheads, sidewalks, pedestrian ramps, and driveways.

PCO#45 - The Change in contract requests additional quantities needed for overrunning items and deduction of underrunning commitment line items used to complete the scope of work.

Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This change in contract is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the City of El Lago homeowners, Harris County, and FEMA. The fiscal impact for this project will come from the 1080 Funding for the Recovery and Resiliency Division subdivisio...