Harris County Logo
File #: 24-2177    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 4/10/2024 In control: Commissioners Court
On agenda: 4/23/2024 Final action:
Title: Request for approval of a change in contract with WadeCon, LLC in connection with Westgate U/R Subdivision Drainage Improvements - 2018, adding 54 calendar days with an addition in the amount of $151,357.62, Job No. 21/0423, UPIN 19103MF14901, Precinct 3, MWDBE Contracted Goal: 28%, MWDBE Participation Goal: 14.15%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19103MF14901; Job No. 21/0423
Vendor/Entity Legal Name (if applicable): WadeCon, LLC

MWDBE Contracted Goal (if applicable): 28%
MWDBE Current Participation (if applicable): 14.15%
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with WadeCon, LLC in connection with Westgate U/R Subdivision Drainage Improvements - 2018, adding 54 calendar days with an addition in the amount of $151,357.62, Job No. 21/0423, UPIN 19103MF14901, Precinct 3, MWDBE Contracted Goal: 28%, MWDBE Participation Goal: 14.15%.
end


Background and Discussion:
This project is located approximately 2.5 miles from Highway US-290 north of North Houston Road, east of N. Eldridge Parkway, and west of Hoffmeister Road. The scope of this project is to regrade 12,850 linear feet of roadside ditches, upsize culverts, replace driveways, and replace existing roadway throughout the subdivision to the Harris County standards.

The Change in contract request new items for the following:

Final Adjustments: Adding 44 calendar days with an addition of $151,357.62 for reconciliation of actual quantities used in construction with estimated quantities used for completing the proposed scope of work.
Holiday Delay - Adding 10 calendar days at the petition of the Precinct, the Contractor stopped excavating concrete pavement work before the Thanksgiving Holidays to make sure that two lanes were open on Jasper Road.

Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Westgate U/R Subdivision Drainage Improvements - (2018).

Alternative Opti...

Click here for full text