Harris County Logo
File #: 24-2175    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 4/10/2024 In control: Commissioners Court
On agenda: 4/23/2024 Final action:
Title: Request for approval to execute an amendment with Kuo & Associates, Inc in the amount of $435,498.00 for Professional Engineering Services to provide improvements to Northpointe Boulevard Segment 1 - from Grant Road to Shaw Road - 2019, UPIN 20104MF1BP01, Precinct 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 20104MF1BP01
Vendor/Entity Legal Name (if applicable): Kuo & Associates, Inc

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval to execute an amendment with Kuo & Associates, Inc in the amount of $435,498.00 for Professional Engineering Services to provide improvements to Northpointe Boulevard Segment 1 - from Grant Road to Shaw Road - 2019, UPIN 20104MF1BP01, Precinct 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end

Background and Discussion:

This project is located at Northpointe Boulevard in Precinct 3. This project will be extending Northpointe Boulevard from Grant Road to Shaw Road. The project includes dual 930' bridges that spans the floodway and two 16 acre detention ponds.

Expected Impact:

This amendment will be proposing the extension of Northpointe Boulevard by providing a 4-lane concrete boulevard with 32" raised median within a 100' ROW and a dual bridges over the Faulkey Gully channel floodway.

Alternative Options:

An alternative would be not to construct the extension of Northpointe Boulevard.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
05/19/2020
16b
Original Agreement Approved by CC.
10/18/2022
32
Amendment #1

Location: Northpointe Drive

Address (if applicable):
Precinct(s): Precinct 3

Fiscal and Personnel Summary
Service...

Click here for full text