Title: Request for approval of a change in contract with Tree Guy, LLC in connection with Recovery Resiliency Division - Crosby Township/MUD Drainage Improvements Franta Street Area 2018 - Clearing of Right-of-Ways and Related Items for Harris County - On-Call Contract, with an addition in the amount of $649.16, Job No. 20/0258-2, UPIN 21208MF1WZ01, Precinct 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 20/0258, UPIN 21208MF1WZ01
Vendor/Entity Legal Name (if applicable): Tree Guy, LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Tree Guy, LLC in connection with Recovery Resiliency Division - Crosby Township/MUD Drainage Improvements Franta Street Area 2018 - Clearing of Right-of-Ways and Related Items for Harris County - On-Call Contract, with an addition in the amount of $649.16, Job No. 20/0258-2, UPIN 21208MF1WZ01, Precinct 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end

Background and Discussion:
The purpose of this project is to improve drainage within specific project areas of Crosby Township/MUD by increasing drainage capacity and reducing the water surface elevations for extreme storm events. The Franta Street area is drained by roadside ditches, which ultimately drain into an existing side lot swale draining southward to the existing drainage ditch serving the adjacent Union Pacific railroad. The railroad ditch drains westward, across Miller Wilson Road, before draining into the upstream reaches of HCFCD Unit No. R106-00- 00, a tributary of Jackson Bayou. The project specific to this change in contract is located at the intersection of Franta Street and Werchan Street, in Crosby, TX, Precinct 3.

The Change in Contract request includes new items for the following:

PCO - 3, Mowing: Additional cost in the amount of $649.16 and added 0 days. Changes include an addition of $649.16 Labor Crew...