File #: 24-2118    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 4/8/2024 In control: Commissioners Court
On agenda: 4/23/2024 Final action:
Title: Request for approval of a change in contract with Main Lane Industries, Ltd, in connection with Transportation improvements near Texas Southern University - Phase II -2019, adding 44 calendar days, with a deduction in the amount of $37,748.56, Job No. 21/0287-3, UPIN 20101MF1JY01, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 21/0287, UPIN 20101MF1JY01
Vendor/Entity Legal Name (if applicable): Main Lane industries, Ltd.

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Main Lane Industries, Ltd, in connection with Transportation improvements near Texas Southern University - Phase II -2019, adding 44 calendar days, with a deduction in the amount of $37,748.56, Job No. 21/0287-3, UPIN 20101MF1JY01, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end

Background and Discussion:
The project includes the improvements of five streets near Texas Southern University (TSU). The major improvement is Blodgett Street from Ennis Road to Scott Street including bike lanes, street and pedestrian lights, streetscape/trees, and other landscape in the median and boost floating bus stops.

Changes include additional linear footage of full depth repair to remove existing curb and gutter along Sampson Street.
* Increasing line item #11: Full Depth Saw Cut and Remove Curb and Gutter - $2,000.00 - 2 days.

Changes include additional time due to Harris County asking contractor to suspend work in an area designated as possibly requiring panel replacements.
* Increasing contract time by 12 days.

Changes include additional conduit and days to provide power from bus pads to new circuit locations.
* Addition of new line item to Furnish labor and material to provide power to all bus shelters - $26,920.65 - 4 days.

Changes include the relocation ...