Harris County Logo
File #: 24-2111    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 4/8/2024 In control: Commissioners Court
On agenda: 4/23/2024 Final action:
Title: Request for approval of a change in contract with Main Lane Industries, LTD, in connection with Intersection Improvement - Katy Hockley at Clay Rd - 2022, adding seven calendar days, with an addition in the amount of $61,096.59, Job No. 22/0230-1, UPIN 23104MF2PP01, Precinct 4, MWDBE Contracted Goal: 32%, MWDBE Current Participation: 22.75%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0230, UPIN 23104MF2PP01
Vendor/Entity Legal Name (if applicable): Main Lane Industries, Ltd.

MWDBE Contracted Goal (if applicable): 32%
MWDBE Current Participation (if applicable): 22.75%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Main Lane Industries, LTD, in connection with Intersection Improvement - Katy Hockley at Clay Rd - 2022, adding seven calendar days, with an addition in the amount of $61,096.59, Job No. 22/0230-1, UPIN 23104MF2PP01, Precinct 4, MWDBE Contracted Goal: 32%, MWDBE Current Participation: 22.75%.
end

Background and Discussion:
This project is for the intersection improvements and roadway widening at Clay and Katy Hockley - Harris County Precinct 4. Change includes costs associated with hydro excavation/potholing at four locations to determine the depths and casing locations of Kinder Morgan gas pipelines in conflict with road widening activities (Adding 4 days).
Change also includes addition of new item associated with the construction of RCB extensions and S.E.Ts. The existing triple run of 6' X 3' Box Culverts are approximately 60% full of mud and debris which limits the volume of drainage intended for the existing infrastructure (Adding 4 days).
Precinct 4 has approved above requests.

Added items:
PCO #1 Cleanout of Existing 6'x3' Box Culverts at Katy Hockey@ Clay Intersection (Cost total = $29,037.36, 3 Additional Days).

PCO #2 Hydro excavation/potholing at four (4) locations to determine the depths and casing of Kinder Morgan pipelines in conflicts with construction work. (Cost total = $32,059.23, 4 Additional Days).





Expected Impact: ...