Title: Request for approval of a change in contract with Teamwork Construction Services, Inc. in connection with Cypress Creek Greenway - 1 Loop Trails at SH 249, adding 71 calendar days, with an addition in the amount of $72,172.00, Job No. 21/0132-3, UPIN 18104MF0HS05, Precinct 3, MWDBE Contracted Goal: 0% (project was awarded prior to launch of County's M/WBE Program).
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 21/0132
Vendor/Entity Legal Name (if applicable): Teamwork Construction Services, Inc.

MWDBE Contracted Goal (if applicable): 0%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Teamwork Construction Services, Inc. in connection with Cypress Creek Greenway - 1 Loop Trails at SH 249, adding 71 calendar days, with an addition in the amount of $72,172.00, Job No. 21/0132-3, UPIN 18104MF0HS05, Precinct 3, MWDBE Contracted Goal: 0% (project was awarded prior to launch of County's M/WBE Program).
end

Background and Discussion:

Project includes the construction of a hike and bike trail at Cypress Creek Greenway both north and south of the SH 249 underpass.

Change includes cost and time for additional drainage upstream of the trail on north side of Cypress Creek as requested by Precinct 3.

* REIMBURSEMENT OF COST AND TIME FOR ADDING 6" CONCRETE , REMOVE RIP RAP ON NORTH SIDE OF THE TRAIL, INSTALL 5" SLOPE PAVING, INSTALLATION OF DRAIN PIPE AND TYPE A INLET ($72,172.00) - 35 DAYS

Change includes time for construction of back slope swale on the back side of the retaining wall.

* TIME FOR CONSTRUCTION OF BACKSLOPE SWALE ON TOP OF RETAILING WALL ON SOUTH SIDE OF THE CREEK ($0.00) - 36 DAYS

Expected Impact:

Change allows for additional drainage upstream of the trail as requested by Precinct 3.

Alternative Options:

Allow storm water runoff to drain across the trail and potentially create a slipping hazard to the pedestrian traffic utilizing the trail.