Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN 19101MF14G01
Vendor/Entity Legal Name (if applicable): ExxonMobil Pipeline Company LLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a consent agreement between ExxonMobil Pipeline Company LLC and Harris County to perform proposed construction in connection with Houmont Park Subdivision Drainage Improvements - 2018, UPIN 19101MF14G01, Precinct 1.
end
Background and Discussion:
This project is located in northeast Harris County in the Greens Bayou (P100-00-00) watershed, east of John Ralston Road and north of Beaumont Highway. The existing drainage system is comprised of three earthen, trapezoidal open channels (P110-00-00, P110-04-00 and P117-00-00) owned and maintained by Harris County Flood Control District (HCFCD). The proposed improvements include re-grading the existing roadside ditches 1,000-feet east and west of the existing drainage channels, replacing inadequate driveway and roadway culverts and channel improvements of the HCFCD Unit Numbers P117-00-00, P110-04-00, and P110-00-00. Other improvements include a detention basin to cause no adverse impacts downstream and Green River Dr. closed system drainage.
Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Houmont Park subdivision. Execution of this agreement will allow drainage improvements including regrading of ditches within ExxonMobil Pipeline Company LLC's easement as designed.
Alternative Options:
If action is not taken, the pipeline comp...
Click here for full text