File #: 24-1608    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/14/2024 In control: Commissioners Court
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Request for approval of a change in contract with The Gonzalez Group, LP., in connection with the Administration Building 1st Floor Commissioner's Court - Remodel/Relocation - 2019, with a deduction in the amount of $328,897.17, Job No. 22/0057-8, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal: 14%, MWDBE Current Participation: 48%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 22/0057
Vendor/Entity Legal Name (if applicable): The Gonzalez Group, LP

MWDBE Contracted Goal (if applicable): 14%
MWDBE Current Participation (if applicable): 48%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with The Gonzalez Group, LP., in connection with the Administration Building 1st Floor Commissioner's Court - Remodel/Relocation - 2019, with a deduction in the amount of $328,897.17, Job No. 22/0057-8, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal: 14%, MWDBE Current Participation: 48%.
end

Background and Discussion:
The Commissioner's Court renovation consists of relocating the court from the 9th floor of the Administration Building to the 1st floor. Scope included a supporting pre-function lobby, enhanced security, conference rooms, private restrooms, and A/V hardware to accommodate the functions of the court.

This change in contract, which results in a net deduction, reconciles the state of the project as it stands in its closing stages. This change in contract is comprised of: added cost of HVAC Testing & Balancing not captured under the original scope of the project, cost of General Conditions to the contractor for days added to the original contractual duration, & a deduction of the cost of proposed Ballistic Glass protection from The Gonzalez Group, LP.'s contract awarded in a previous change order.


Expected Impact:
These changes allow the completion of closing the contract with The Gonzalez Group, LP.


Alternative Options:
Should we not move forward with this change in contract, these items will remain unreconciled delaying the closeout of the contract and project.