Title: Request for approval of a change in contract with The Gonzalez Group, LP., in connection with the Administration Building 1st Floor Commissioner's Court - Remodel/Relocation - 2019, with a deduction in the amount of $328,897.17, Job No. 22/0057-8, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal: 14%, MWDBE Current Participation: 48%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 22/0057

Vendor/Entity Legal Name (if applicable): The Gonzalez Group, LP

 

MWDBE Contracted Goal (if applicable): 14%

MWDBE Current Participation (if applicable): 48%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with The Gonzalez Group, LP., in connection with the Administration Building 1st Floor Commissioner’s Court - Remodel/Relocation - 2019, with a deduction in the amount of $328,897.17, Job No. 22/0057-8, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal: 14%, MWDBE Current Participation: 48%.

end

 

Background and Discussion:

The Commissioner’s Court renovation consists of relocating the court from the 9th floor of the Administration Building to the 1st floor. Scope included a supporting pre-function lobby, enhanced security, conference rooms, private restrooms, and A/V hardware to accommodate the functions of the court.

 

This change in contract, which results in a net deduction, reconciles the state of the project as it stands in its closing stages. This change in contract is comprised of: added cost of HVAC Testing & Balancing not captured under the original scope of the project, cost of General Conditions to the contractor for days added to the original contractual duration, & a deduction of the cost of proposed Ballistic Glass protection from The Gonzalez Group, LP.’s contract awarded in a previous change order.

 

 

Expected Impact:

These changes allow the completion of closing the contract with The Gonzalez Group, LP.

 

 

Alternative Options:

Should we not move forward with this change in contract, these items will remain unreconciled delaying the closeout of the contract and project.

 

 

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

06-14-2022

214

Approved - Contract Award - Request for approval of an award on the basis of best proposal meeting requirements to The Gonzalez Group LP in the amount of $4,370,314 for the construction price for relocation of Harris County Commissioners Court from Level 9 to Level 1 of the Administration Building, subject to applicable bond(s) to be received for the construction price (220057), MWDBE Contracted Goal: 14%

11-29-2022

36

Approved - CIC# 22/0057-1 - Request for approval of a change in contract with The Gonzalez Group, LP., in connection with Administration Building 1st Floor Commissioner's Court - Remodel/Relocation - 2019, with an addition in the amount of $25,064.12, Job No. 22/0057-1, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal 14%, MWDBE Current Participation 14%.

01-10-2023

49

Approved - CIC# 22/0057-2 - Request for approval of a change in contract with The Gonzalez Group, LP., in connection with Administration Building 1st Floor Commissioner's Court - Remodel/Relocation - 2019, with an addition in the amount of $41,786.11, Job No. 22/0057-2, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal 14%, MWDBE Current Participation 14%.

02-21-2023

59

Approved - CIC# 22/0057-3 - Request for approval of a change in contract with The Gonzalez Group, LP., in connection with Administration Building 1st Floor Commissioner's Court - Remodel/Relocation - 2019, with an addition in the amount of $42,597.41, Job No. 22/0057-3, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal 14%, MWDBE Current Participation 14%.

04-04-2023

54

Approved - CIC# 22/0057-4 - Request for approval of a change in contract with The Gonzalez Group, LP., in connection with Administration Building 1st Floor Commissioner's Court - Remodel/Relocation - 2019, with an addition in the amount of $23,388.08, Job No. 22/0057-4, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal: 14%, MWDBE Current Participation: 48%

05-16-2023

62

Approved - CIC# 22/0057-5 - Request for approval of a change in contract with The Gonzalez Group, LP., in connection with Administration Building 1st Floor Commissioner's Court - Remodel/Relocation - 2019, with an addition in the amount of $28,944.32, Job No. 22/0057-5, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal 14%, MWDBE Current Participation 48%.

08-08-2023

46

Approved - CIC# 22/0057-6 - Request for approval of a change in contract with The Gonzalez Group, LP., in connection with Administration Building 1st Floor Commissioner's Court - Remodel/Relocation - 2019, adding 282 calendar days, with an addition in the amount of $502,430.83, Job No. 22/0057-6, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal 14%, MWDBE Current Participation 48%.

12-19-2023

58

Approved - CIC# 22/0057-7 - Request for approval of a change in contract with The Gonzalez Group, LP., in connection with the Administration Building 1st Floor Commissioner's - Court Remodel/Relocation - 2019, with an addition in the amount of $43,801.41, Job No. 22/0057-7, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal: 14%, MWDBE Current Participation: 48%.

01-30-2024

129

Approved - Request for approval to release Retainage to The Gonzalez Group, LP., in connection with the Administration Building 1st Floor Commissioner’s - Court Remodel/Relocation - in the amount of $227,850.75. Job No. 22/0057-7, UPIN 20035MF1ER01, Precinct 1, MWDBE Contracted Goal 14%, MWDBE Current Participation 48%.

 

Location:

Address (if applicable): 1001 Preston St., Houston, TX 77002

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

($328,897.17)

($328,897.17)

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

($328,897.17)

($328,897.17)

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

($328,897.17)

($328,897.17)

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: March 26, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Ross Hosket P.E., CFM, Env SP, Interim director of Capital Project Facility, Engineering

 