File #: 24-1547    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/14/2024 In control: Commissioners Court
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Request for approval of a change in contract with WadeCon, LLC in connection with Greenhouse Road-North Approach Cypress Creek Bridges to Mound Road; Mound Road-458 feet East of Crossland Park Lane to Greenhouse Road - 2020, with an addition in the amount of $105,732.47, Job No. 21/0408-2, UPIN 201033952823, Precinct 3, MWDBE Contracted Goal: 13%, MWDBE Current Participation: 12.68%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No: 21/0408
Vendor/Entity Legal Name (if applicable): WadeCon, LLC

MWDBE Contracted Goal (if applicable): 13%
MWDBE Current Participation (if applicable): 12.68%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with WadeCon, LLC in connection with Greenhouse Road-North Approach Cypress Creek Bridges to Mound Road; Mound Road-458 feet East of Crossland Park Lane to Greenhouse Road - 2020, with an addition in the amount of $105,732.47, Job No. 21/0408-2, UPIN 201033952823, Precinct 3, MWDBE Contracted Goal: 13%, MWDBE Current Participation: 12.68%.
end

Background and Discussion:
Project includes completion of the second half of the concrete boulevard pavement section for Greenhouse Road, from North Approach Cypress Creek Bridges to Mound Road and Mound Road and from 458ft East of Crossland Park Lane to Greenhouse Road.

This change in contracts includes:
* Cost increase for hot mix asphaltic concrete base coarse (8-inch black base), reinforced concrete pavement (10-inch depth), reinforced concrete driveways (10-inch depth) - high early strength, reinforced concrete driveways (6-inch depth) - high early strength and lime slurry.
* Cost for installation of 8-inch solid white striping, removal of 4-inch and 24-inch striping.

Expected Impact:
Change allows the contractor to be compensated for change in price per contract and to be compensated for striping which was in the plan but missed in the bid tab.

Alternative Options:
Maintain the original scope of the project.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environme...