Harris County Logo
File #: 24-0907    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 2/12/2024 In control: Commissioners Court
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Request for approval of a contract award with Consor Engineers, LLC in the amount of $133,705.00 for Professional Engineering Services for the design of Bridge Repair - Stuebner Airline Rd Bridge K100 - 2024, UPIN 24103MF3A801, Precinct 3, Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible.
Attachments: 1. 24-0907-Consultant-UPIN 24103MF3A801-Consor Engineers LLC- Bridge Repair --24GEN0352
Department: Commissioner, Precinct 3
Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, ENV SP County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 24103MF3A801
Vendor/Entity Legal Name (if applicable): Consor Engineers LLC

MWDBE Contracted Goal (if applicable): 0
MWDBE Current Participation (if applicable): 0
Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible

Request Summary (Agenda Caption):
title
Request for approval of a contract award with Consor Engineers, LLC in the amount of $133,705.00 for Professional Engineering Services for the design of Bridge Repair - Stuebner Airline Rd Bridge K100 - 2024, UPIN 24103MF3A801, Precinct 3, Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible.
end

Background and Discussion:
Harris County engaged with Consor Engineers LLC to conduct site investigation and provide design recommendation for the repairs at Stuebner Bridge to ensure longevity of the bridge.

Expected Impact:
The project will address current bridge repairs needed to ensure mobility for the community.

Alternative Options:
If no action is taken, the bridge will continue to experience deterioration that would need larger scale repairs in the future.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
01/30/2024
131
Request for approval to negotiate with Consor Engineers LLC for Professional Engineering Services for the design of Bridge Repair- Stuebner Airline Rd Bridge K100-2024, UPIN 24103MFA801, Precinct 3.




Location:
Address (if applicable):
Precinct(s): Precinct 3

Fiscal and Personnel Summary
Service Name
Stuebner Airline Bridge


Current Fiscal Year Cost
Annual Fiscal Cost

Labor
Non-Labor
Total
Recurring Expenses
Funding Sources

Existing Bu...

Click here for full text