Department: Commissioner, Precinct 3
Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, ENV SP County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 24103MF3A801
Vendor/Entity Legal Name (if applicable): Consor Engineers LLC
MWDBE Contracted Goal (if applicable): 0
MWDBE Current Participation (if applicable): 0
Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible
Request Summary (Agenda Caption):
title
Request for approval of a contract award with Consor Engineers, LLC in the amount of $133,705.00 for Professional Engineering Services for the design of Bridge Repair - Stuebner Airline Rd Bridge K100 - 2024, UPIN 24103MF3A801, Precinct 3, Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible.
end
Background and Discussion:
Harris County engaged with Consor Engineers LLC to conduct site investigation and provide design recommendation for the repairs at Stuebner Bridge to ensure longevity of the bridge.
Expected Impact:
The project will address current bridge repairs needed to ensure mobility for the community.
Alternative Options:
If no action is taken, the bridge will continue to experience deterioration that would need larger scale repairs in the future.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
01/30/2024 |
131 |
Request for approval to negotiate with Consor Engineers LLC for Professional Engineering Services for the design of Bridge Repair- Stuebner Airline Rd Bridge K100-2024, UPIN 24103MFA801, Precinct 3. |
|
|
|
Location:
Address (if applicable):
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
Stuebner Airline Bridge |
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Other Fund 3002 |
$ |
$133,705.00 |
$133,705.00 |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$ 133,705.00. |
$133,705.00 |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$ 133,705.00. |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: February 27, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Dr. Hatem Bastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department
Attachments (if applicable): Contract