File #: 24-0885    Version: 1 Name:
Type: Contract - Termination Status: Passed
File created: 2/12/2024 In control: Commissioners Court
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Request for approval of a Mutual Termination Agreement with Isani Consultants, LP in connection with improvements to Wallisville Rd - from 500' west of John Martin Rd to 350' west of Garth Road, UPIN 19102MF0YS01, Precinct 3 (Previously Precinct 2).
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Termination

Project ID (if applicable): UPIN 19102MF0YS01
Vendor/Entity Legal Name (if applicable): Isani Consultants, LP

MWDBE Contracted Goal (if applicable): 0%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title

Request for approval of a Mutual Termination Agreement with Isani Consultants, LP in connection with improvements to Wallisville Rd - from 500' west of John Martin Rd to 350' west of Garth Road, UPIN 19102MF0YS01, Precinct 3 (Previously Precinct 2).
end

Background and Discussion:

The professional services contract was originally executed on October 23, 2019 with Isani Consultants, LP for an amount not to exceed $729,502. Harris County entered into two amendments made on January 25, 2020 for $764,372.00 (addition of $34,870) and on March 14, 2023 for $929,993.40 (addition of $165,621.40) to the contract. This project has been mutually agreed upon for termination. An amount of $62,755.00 in unexpended funds will be returned to the County as part of the termination of the agreement.

Expected Impact:

Termination of the agreement and return of the remaining funds.

Alternative Options:

No alternative option. Both parties agree to mutually terminate the agreement

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
5/1/18
1.f.1-11
Authorization to negotiate approved on court agenda
10/23/18
1.d.1-11
Professional Engineering Services agreement approved on court agenda
1/28/20
1.g.1-12
First amendment to Professional Engineering Services agreement approve...