File #: 23-6739    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/3/2023 In control: Commissioners Court
On agenda: 11/14/2023 Final action: 11/14/2023
Title: Request for approval of a change in contract with Divisionone Construction LLC., in connection with Peden Building (Harvey), adding 14 calendar days, with an addition in the amount of $197,284.92, Job No. 21/0295-6, UPIN 18035MF0W501, Precinct 2, (project was awarded prior to launch of County's M/WBE Program).
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): MF0W5 (21/0295)
Vendor/Entity Legal Name (if applicable): Divisionone Construction LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title

Request for approval of a change in contract with Divisionone Construction LLC., in connection with Peden Building (Harvey), adding 14 calendar days, with an addition in the amount of $197,284.92, Job No. 21/0295-6, UPIN 18035MF0W501, Precinct 2, (project was awarded prior to launch of County's M/WBE Program).
end


Background and Discussion:
Harris County Peden Building is a complete renovation located at 600 North San Jacinto Street, modernization of three hydraulic passenger elevators and installation of new floodproofing. This change in contract entails items required for life safety per code, network requirements, and modifications to the elevators with 14 additional calendar days.

Expected Impact:
This change in contract will bring the project up to code compliance and will allow the completion of the project in accordance with the original intent of the project.

Alternative Options:
Should we decide not to move forward with this change order we will not be able to get our certificate of occupancy per code compliance.

Alignment with Goal(s):
X Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
11/9/2021
187
Contract Award
10/11/2022
34
Change in Contract #21/0295-1
12/13/2022
62
Change in Contract #21/0295-2
01/31/2023
38
Change in Contract #...