Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Public Necessity
Project ID (if applicable): Q134-00-00-E001
Vendor/Entity Legal Name (if applicable): N/A
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to decree that the Harris County Flood Control District project serve a public purpose and public necessity requires that the Harris County Real Property Division be directed to acquire one fee simple tract for the public project known as Q134-00-00 and Q134-01-00 Channel Improvement PER and Design, for the purpose of channel improvements. (Cedar Bayou Watershed, Bond ID F-45, Project ID Q134-00-00-E001, Precinct 3).
end
Background and Discussion:
Additional right-of-way is needed for maintenance and future drainage improvements in the watershed were identified based on the Q134-00-00-P001 Advanced Feasibility Study.
Expected Impact:
The future drainage improvements are part of an ultimate drainage solution identified in the Q134-00-00-P001 Advanced Feasibility Study.
Alternative Options:
The alternative should this not be approved is that the district will not be able to acquire the right-of-way under this project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any): N/A
Date
Agenda Item #
Action Taken
Location: N/A
Address (if applicable):
Precinct(s): Precinct 3
Fiscal and Personnel Summary
Service Name
N/A
FY 23
FY 24
Next 3 FYs
Incremental Expenditures (do NOT write values in thousands or millions)
Labor Expenditures
$
$
$
Non-Labor Expenditures
$
$
$
Total Incremental Expenditures...
Click here for full text