Harris County Logo
File #: 23-2880    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/9/2023 In control: Commissioners Court
On agenda: 5/16/2023 Final action: 5/16/2023
Title: Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with Tidwell Road from west of Greens Bayou to CE King Pkwy, adding 140 calendar days, with an addition in the amount of $180,333.94, Job No. 19/0305-2, UPIN 16101MF0H401, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 19/0305
Vendor/Entity Legal Name (if applicable): Allgood Construction Co., Inc.

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with Tidwell Road from west of Greens Bayou to CE King Pkwy, adding 140 calendar days, with an addition in the amount of $180,333.94, Job No. 19/0305-2, UPIN 16101MF0H401, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end

Background and Discussion:

Project includes the construction of Tidwell Road 4-Lane Concrete Boulevard and Replace Greens Bayou Bridge.

Change includes additional time and compensation associated with existing bid item quantity increases as confirmed by the Engineer of Record. Major increased items include constructing detour 8" black base, low profile concrete barrier, temporary SLP shoring, and remove existing water line and temporary waterline (7 days and $132299.75).

Change also includes additional time and compensation for the following new items of work:
* New Type 5 ADA ramp at corner of John Ralston and Tidwell (1 day and $2560.20).
* New concrete bus pads at the request of Precinct 1 and Harris County Transit Authority (2 days, $11157.50).
* Special project signs at the request of Precinct 1 (0 days, $2600.00)
* Roller supports as opposed to flat supports for water line on bridge (0 days, $16264.70)
* Additional concrete driveways (1 day, $6951.79)
* Adjustment of an existing waterline due to confli...

Click here for full text