Title: Request by the Flood Control District for approval to accept from the Federal Emergency Management Agency grant funds in the amount of $8,250,000, with a required match of $3,658,303, for the Westador Stormwater Detention Basin Program (K500-27-00-E001).
4epartment: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Supplemental RCA

Type of Request: Grant

Project ID (if applicable): K500-27-00-E001
Vendor/Entity Legal Name (if applicable): N/A

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request by the Flood Control District for approval to accept from the Federal Emergency Management Agency grant funds in the amount of $8,250,000, with a required match of $3,658,303, for the Westador Stormwater Detention Basin Program (K500-27-00-E001).
end

Background and Discussion:
It is recommended that the HCFCD be authorized to accept the grant award funds from the Department of Homeland Security (DHS) Fiscal Year 2022 Pre-Disaster Mitigation (Congressionally Directed) Grant Program to fund the design engineering and construction of stormwater detention basins (K500-27-00-E001) along the southern bank of Cypress Creek (K100-00-00) between Bamwood Road and Red Oak Drive. An existing Interlocal Agreement between Westador MUD and HCFCD, allows HCFCD to construct and maintain a stormwater detention facility on Westador MUD property. The recommended project consisting of Phase 1 and 2 requires only the transfer of a 60 ft x 60 ft roadway ROW on Tigris Lane between Harris County and HCFCD. The funding is available specifically for this project in the FY22 Federal Budget and was submitted by US Congressman Dan Crenshaw, representing the 2nd District of Texas.

The proposed K500-27-00-E001 Westador Stormwater Detention Basin Project will further improve riverine flood risk in Cypress Creek. The two basins will store up to 200.95 acre-feet during severe rainfall events. Period of Performance (POP) for the grant is from September 13th, 2022 to September 12th, 2025.

Expected...