Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): Q114-00-00-E001
Vendor/Entity Legal Name (if applicable): Binkley & Barfield, Inc.
MWDBE Contracted Goal (if applicable): 22%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of an agreement with Binkley & Barfield, Inc., in the amount of $1,086,297, to provide preliminary engineering and design services in support of Cedar Bayou regional detention and channel improvements project HCFCD Unit Q114-00-00. (Cedar Bayou Watershed, Bond ID F-42, Project ID Q144-00-00-E001, Agreement No. 2022-90, Precinct 3, MWDBE Contracted Goal: 22%).
end
Background and Discussion:
HCFCD Unit Q114-00-00 has a long history of flooding and has been included in previous Cedar Bayou Flood Risk Reduction Study. The preliminary engineering report (PER) is needed to determine the best use of flood mitigation along this channel, to identify the require ROW and support other large-scale flood reduction efforts in the Cedar Bayou Watershed. The preliminary engineering effort is complex and requires review of other past and ongoing efforts along Q114-00-00 and the surround area, detailed H&H modeling, right-of-way (ROW) identification and conceptual design. This court action is to proceed with preparing a Preliminary Engineering Report (PER) and conceptual design for the Q114-00-00 regional detention and channel improvements project.
Expected Impact:
This project is part of the Cedar Bayou Bond Implementation Program that could reduce flood risks in the area. The outcome of the preliminary engineering report is to recommend a flood risk mitigation project along Q114-00-00, potential acquisition of additional ROW, defin...