File #: 23-0184    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 12/28/2022 In control: Commissioners Court
On agenda: 1/10/2023 Final action: 1/10/2023
Title: Request for approval of an agreement with Binkley & Barfield, Inc., in the amount of $1,086,297, to provide preliminary engineering and design services in support of Cedar Bayou regional detention and channel improvements project HCFCD Unit Q114-00-00. (Cedar Bayou Watershed, Bond ID F-42, Project ID Q144-00-00-E001, Agreement No. 2022-90, Precinct 3, MWDBE Contracted Goal: 22%).
Attachments: 1. 011023 AGMT BINKLEY BARFIELD 2022-90 PCT 3 backup

Department: Flood Control District

Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): Q114-00-00-E001                     

Vendor/Entity Legal Name (if applicable): Binkley & Barfield, Inc.

 

MWDBE Contracted Goal (if applicable): 22%

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of an agreement with Binkley & Barfield, Inc., in the amount of $1,086,297, to provide preliminary engineering and design services in support of Cedar Bayou regional detention and channel improvements project HCFCD Unit Q114-00-00. (Cedar Bayou Watershed, Bond ID F-42, Project ID Q144-00-00-E001, Agreement No. 2022-90, Precinct 3, MWDBE Contracted Goal: 22%).

end

 

Background and Discussion:

HCFCD Unit Q114-00-00 has a long history of flooding and has been included in previous Cedar Bayou Flood Risk Reduction Study. The preliminary engineering report (PER) is needed to determine the best use of flood mitigation along this channel, to identify the require ROW and support other large-scale flood reduction efforts in the Cedar Bayou Watershed.  The preliminary engineering effort is complex and requires review of other past and ongoing efforts along Q114-00-00 and the surround area, detailed H&H modeling, right-of-way (ROW) identification and conceptual design. This court action is to proceed with preparing a Preliminary Engineering Report (PER) and conceptual design for the Q114-00-00 regional detention and channel improvements project.

 

Expected Impact:

This project is part of the Cedar Bayou Bond Implementation Program that could reduce flood risks in the area.  The outcome of the preliminary engineering report is to recommend a flood risk mitigation project along Q114-00-00, potential acquisition of additional ROW, define preliminary permitting requirements and identify stakeholder coordination efforts.

 

Alternative Options:

The alternative should this agreement request not be approved is that the District will not be able to proceed with PER stage of the project lifecycle to determine recommended improvements to reduce flood risks in the area.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

10/26/2021

124.

ATN

 

Location: Q114-00-00 Tributary in Cedar Bayou watershed east of Harris County

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

4.a.5 - Planning Services

 

FY 23

FY 24

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$1,086,297

$

$

Total Incremental Expenditures

$1,086,297

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Bonds

$1,086,297

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$1,086,297

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$1,086,297

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 10, 2023

Anticipated Implementation Date (if different from Court date):

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

Attachments (if applicable): Agreement and Map