Title: Request for approval to execute an agreement with MBCO Engineering, LLC in the amount of $88,495.00 for Professional Engineering Services to provide improvements to the traffic signal at the intersection of Clinton Drive and Galena Manor, UPIN 23102MF2QW01, Precinct 2, MWDBE Contracted Goal 100%.
Attachments: 1. 23-0127 Consultant - MBCO Clinton Dr at Galena Manor Dr P2.pdf
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN 23102MF2QW01
Vendor/Entity Legal Name (if applicable): MBCO Engineering, LLC

MWDBE Contracted Goal (if applicable): 100%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with MBCO Engineering, LLC in the amount of $88,495.00 for Professional Engineering Services to provide improvements to the traffic signal at the intersection of Clinton Drive and Galena Manor, UPIN 23102MF2QW01, Precinct 2, MWDBE Contracted Goal 100%.
end

Background and Discussion:
Traffic signals are installed to improve the safety operation of an intersection. The existing traffic signal at Clinton Drive and Galena Manor Drive was installed 38 years ago and it is recommended to rebuild the traffic signal to current standards and specifications. Rebuilding the traffic signal will bring the infrastructure to current standards/specifications and reduce overall maintenance cost. It will also significantly reduce the risk of failure during a catastrophic event.

Expected Impact:
Rebuilding the traffic signal will bring the infrastructure to current standards and specifications and reduce overall maintenance cost. It will also significantly reduce the risk of failure during a catastrophic event.

Alternative Options:
To continue to maintain the existing traffic signal and slowly replace degrading parts as they fail. This may potentially be more costly and incurs a risk of failure due to aging infrastructure, which is a safety concern.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Serv...

Click here for full text