Department: County Engineer
Department Head/Elected Official: Milton Rahman, Ph.D., P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 22101MF2F101
Vendor/Entity Legal Name (if applicable): EJES, Inc.
MWDBE Contracted Goal (if applicable): 100%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with EJES, Inc. in the amount of $373,264.50 for Professional Engineering Services to provide improvements to Asphalt Overlay Project along Forest Acres Subdivision, UPIN 22101MF2F101, Precinct 1, MWDBE Contracted Goal 100%.
end
Background and Discussion:
Precinct has continued to develop their roadway rehabilitation program and is preparing to improve roadways along Cline Rd, Winfield Rd, Nightingale Dr, and Forest Acre Dr.
Project consists of roadside ditch improvements, rehabilitation, or full depth reconstruction of approximately 15,140 ft. (2.87 Miles) of asphalt roadway.
Expected Impact:
Reconstruction and rehabilitation of the proposed roadways will improve drainage and pavement conditions.
Alternative Options:
If no action is taken; the proposed roadway improvements will be delayed.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
11/09/2021
75
Approval of authorization to negotiate.
Location:
Address (if applicable): Forest Acres Subdivision
Precinct(s): Precinct 1
Fiscal and Personnel Summary
Service Name
Professional Services
SFY 22
FY 23
Next 3 FYs
Incremental Expenditures (do NOT write values in thousands or millions)
Labor Expenditures
$
$
$
Non-Labor Expenditures
$373,264.50
$
$
Total Incremental Expend...