File #: 22-5494    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/6/2022 In control: Commissioners Court
On agenda: 9/13/2022 Final action: 9/13/2022
Title: Request for approval of a change in contract with Main Lane Industries, LTD in connection with Spring Cypress at Louetta Apartments (Sovereign Spring Cypress Apartments) Drainage Improvements - 2018, with an addition in the amount of $96,375.00, Job No. 21/0217-1, UPIN 19104MF16801, Precinct 3, MWDBE Contracted Goal: 12%, MWDBE Current Participation: 5.34%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 21/0217
Vendor/Entity Legal Name (if applicable): Main Lane Industries, LTD

MWDBE Contracted Goal (if applicable): 12%
MWDBE Current Participation (if applicable): 5.34%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Main Lane Industries, LTD in connection with Spring Cypress at Louetta Apartments (Sovereign Spring Cypress Apartments) Drainage Improvements - 2018, with an addition in the amount of $96,375.00, Job No. 21/0217-1, UPIN 19104MF16801, Precinct 3, MWDBE Contracted Goal: 12%, MWDBE Current Participation: 5.34%.
end

Background and Discussion:

This project is located in Cypress Creek Watershed, on Louetta Road, west of IH 45. The scope and proposed improvements include converting the roadside ditch to an underground concrete box storm sewer trunk system to outfall to Senger Gully, along with removing undersize driveway culverts. Changes requested by Precinct during design review included extension and grade change of proposed ditch. New Items included Removal of Guard Rail, Removal and Replacement of Rock Wall, Removal of SET, 8" CCP Storm Pipe, 15" CCP Storm Pipe, 18"RCP, 30"RCP, 36"RCP, Type C Manhole, Type D inlet, SET 18", SET 36". Design was approved by the EOR.

Expected Impact:

Changes allow for addition of new bid items to complete the project in accordance with the original intent of the project and in compliance with Precinct requests.

Alternative Options:

Maintain the original scope of the project.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service