File #: 21-6434    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/15/2021 In control: Commissioners Court
On agenda: 11/30/2021 Final action: 11/30/2021
Title: Request for approval to execute an amendment with GC Engineering, Inc. in the amount of $49,632.00 for Professional Engineering Services to provide improvements to Telge Road Segment 2, UPIN 15104MF0DN02, Precinct 4.
Attachments: 1. 21-6434 Consultant - GC Engineering, Inc P4.pdf
Department: County Engineer
Department Head/Elected Official: Loyd Smith, P.E., Interim County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 15104MF0DN02
Vendor/Entity Legal Name (if applicable): GC Engineering, Inc.
MWDBE Participation (if applicable): N/A

Request Summary (Agenda Caption):
title
Request for approval to execute an amendment with GC Engineering, Inc. in the amount of $49,632.00 for Professional Engineering Services to provide improvements to Telge Road Segment 2, UPIN 15104MF0DN02, Precinct 4.
end

Background and Discussion:
Harris County engaged GC Engineering Inc. to study and design the project in 2015, and now seeks GC Engineering, Inc. to assist with additional design services.
The goal of improving Telge Road 2 is to achieve a level of service to meet current and future traffic volumes, reduce delays, and reduce structural flooding of adjacent residences businesses, and schools.
GC Engineering, Inc. is uniquely qualified to perform these professional services as GC Engineering is the engineer of record for the project.


Expected Impact:
Reconstructing this road will improve pavement conditions and enhance drainage capacity, thereby improving mobility and safety for all road users and flood resiliency for all adjacent properties.

Alternative Options:
Alternative options include choosing not to reconstruct Telge Road and the accompanying improved drainage system. Another alternative would be to not perform the additional design effort which would need to be addressed later during construction, resulting in a higher cost to the County


Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
x Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
4/28/2015
I.1.a.2.c.1
Awarded professional services agreement
1/7/2020
I.1.f.25
Amendment #...