File #: 21-6434    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/15/2021 In control: Commissioners Court
On agenda: 11/30/2021 Final action: 11/30/2021
Title: Request for approval to execute an amendment with GC Engineering, Inc. in the amount of $49,632.00 for Professional Engineering Services to provide improvements to Telge Road Segment 2, UPIN 15104MF0DN02, Precinct 4.
Attachments: 1. 21-6434 Consultant - GC Engineering, Inc P4.pdf

Department: County Engineer

Department Head/Elected Official: Loyd Smith, P.E., Interim County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN 15104MF0DN02

Vendor/Entity Legal Name (if applicable): GC Engineering, Inc.

MWDBE Participation (if applicable): N/A

 

Request Summary (Agenda Caption):

title

Request for approval to execute an amendment with GC Engineering, Inc. in the amount of $49,632.00 for Professional Engineering Services to provide improvements to Telge Road Segment 2, UPIN 15104MF0DN02, Precinct 4.

end

 

Background and Discussion:

Harris County engaged GC Engineering Inc. to study and design the project in 2015, and now seeks GC Engineering, Inc. to assist with additional design services.

The goal of improving Telge Road 2 is to achieve a level of service to meet current and future traffic volumes, reduce delays, and reduce structural flooding of adjacent residences businesses, and schools.

GC Engineering, Inc. is uniquely qualified to perform these professional services as GC Engineering is the engineer of record for the project.  

 

 

Expected Impact:

Reconstructing this road will improve pavement conditions and enhance drainage capacity, thereby improving mobility and safety for all road users and flood resiliency for all adjacent properties.

 

Alternative Options:

Alternative options include choosing not to reconstruct Telge Road and the accompanying improved drainage system. Another alternative would be to not perform the additional design effort which would need to be addressed later during construction, resulting in a higher cost to the County

 

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

x Transportation

x Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

4/28/2015

I.1.a.2.c.1

Awarded professional services agreement

1/7/2020

I.1.f.25

Amendment #1

5/19/2020

I.1.g.14

Amendment #2

9/28/2021

21.14

Amendment #3

 

 

Location:

Address (if applicable): N/A

Precinct(s): Precinct 4

 

 

Fiscal and Personnel Summary

Service Name

Professional Services

 

FY 21-22

FY 22

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$1,096,336.78

$

$

Total Incremental Expenditures

$1,096,336.78

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

1070 - Mobility Fund

$1,046,704.78

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$1,046,704.78

$

$

Additional Budget Requested

1070 - Mobility Fund

$49,632.00

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$49,632.00

$

$

Total Funding Sources

$1,096,336.78

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

 

Anticipated Implementation Date: November 30, 2021

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Wade J. Himel, P.E., Senior Project Manager, Harris County Engineering Department

 

Attachments (if applicable): Agreement