Harris County Logo
File #: 21-6345    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/15/2021 In control: Commissioners Court
On agenda: 11/30/2021 Final action: 11/30/2021
Title: Request for approval of a renewal option with Texas Materials Group, Inc. D/B/A Gulf Coast for riprap and related items in Precinct 4 for the period of January 4, 2022 - January 3, 2023 at a cost of $100,000 (200313).
Attachments: 1. 21-6345 Renewal 200313 Texas Material Group, Inc. DBA Gulf Coast.pdf
Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 200313
Vendor/Entity Legal Name (if applicable): Texas Materials Group, Inc. D/B/A Gulf Coast
MWDBE Participation (if applicable): N/A

Request Summary (Agenda Caption):
title
Request for approval of a renewal option with Texas Materials Group, Inc. D/B/A Gulf Coast for riprap and related items in Precinct 4 for the period of January 4, 2022 - January 3, 2023 at a cost of $100,000 (200313).
end

Background and Discussion:

Precinct 4 requested the renewal process be completed for an on-call term contract rip rap and related items.

Expected Impact:

Precinct 4 will have continued access to rip rap and related items.

Alternative Options:

Precinct 4 would be required to determine other resources for rip rap and related items.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
x Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
N/A
N/A
N/A


Location:
Address (if applicable):
Precinct(s): Precinct 4


Fiscal and Personnel Summary
Service Name
-
FY 21-22
Estimates



FY 22
Next 3 FYs
Incremental Expenditures
Labor Expenditures
-
-
-
Non-Labor Expenditures
$100,000.00
-
-
Total Incremental Expenditures
$100,000.00
-
-
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify)
Existing
Budget
-
-
-
-

-
-
-
-

-
-
-
-
Total Current Budget
-
-
-
Additional Budget Requested
PCT 4 -
$100,000.00
-
-

-
-
-
-

-
-
-
-
Total Additional Budget Requested
-
-
-
Total Funding Sources
$100,000.00
-
-
Personnel (Fill out section only if requesting new PCNs)
Current Position Count for Service
-
-
-
Additional Positions Requested
-
-
-
Total Personnel
-
-
-


Anticipated Implementation Date: November 30, 2021 Court Date
Emergency/Disas...

Click here for full text