Department: County Engineer
Department Head/Elected Official: Loyd Smith, P.E., Interim County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): UPIN 16102MF0HY02
Vendor/Entity Legal Name (if applicable): Balmoral LT, LLC
MWDBE Participation (if applicable): N/A
Request Summary (Agenda Caption):
title
Request for approval of an interlocal agreement with Balmoral LT, LLC for the County to include certain additional improvements at various locations to facilitate future development by Balmoral, as part of the County's project to construct improvements in connection with Woodland Hills Drive Phase 2 New Construction from Sunset Breeze Drive to Woodland Path Drive, UPIN 16102MF0HY02, Precinct 2.
end
Background and Discussion:
County intends to construct roadway and drainage improvements on Woodland Hills Drive Phase 2.
Expected Impact:
In performing these services, the County will help to facilitate future access and future developments to an existing undeveloped area.
Alternative Options: N/A
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
3/8/2016
Professional Service Agreement with Weisser Engineering Company, Inc.
3/8/2016
Professional Service Agreement with Brown and Gay Engineers
Location:
Address (if applicable): Woodland Hills Drive Phase 2 from North Sunset Breeze Drive to Woodland Path Drive
Precinct(s): Precinct 2
Fiscal and Personnel Summary
Service Name
-
FY 21-22
Estimates
FY 22
Next 3 FYs
Incremental Expenditures
Labor Expenditures
-
-
-
Non-Labor Expenditures
-
-
-
Total Incremental Expenditures
-
-
-
Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify)
Existing
Budget
-
-
-
-
-
-
-
-
-
-
-
-
Total Current Budget
-
-
-
Additional Budget Re...
Click here for full text