Title: Request for approval to execute an agreement with PGAL, Inc. in the amount of $189,618.23 for Professional Engineering Services for improvements to West Gulf Bank Road from IH-45 to East of Airline Drive, UPIN 19101MF0XV01, Precinct 1.
Attachments: 1. 21-4751 Consultant - PGAL, Inc P1.pdf
Department: County Engineer

Department Head/Elected Official: John R. Blount, P.E., County Engineer


Regular or Supplemental RCA:
? Regular RCA
? Supplemental RCA


Type of Request: Contract - Award

Project ID (if applicable): 19101MF0XV01
Vendor/Entity Legal Name (if applicable): PGAL, Inc.
MWDBE Participation (if applicable): N/A

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with PGAL, Inc. in the amount of $189,618.23 for Professional Engineering Services for improvements to West Gulf Bank Road from IH-45 to East of Airline Drive, UPIN 19101MF0XV01, Precinct 1.
end

Background and Discussion:

The County engaged PGAL, Inc. to study and design the project in 2018, and now seeks PGAL Inc. to assist and advise the County during project construction. The goal of improving W. Gulf Bank from IH-45 to Airline is to achieve a level of service to meet current and future traffic volumes, reduce delays, and provide safe mobility for pedestrians and bicyclists and reduce structural flooding of adjacent residences and businesses, and schools.


Expected Impact:

The project will address current and future traffic volumes, reduce delays, and provide safe mobility for pedestrians and bicyclists and reduce structural flooding of adjacent residences, businesses, and schools.



Alternative Options:
If no action is taken the project may experience delays in construction staking, review of submittals and RFI's as well as traffic control plans as required by the agreement.




Alignment with Goal(s):
? Justice and Safety
? Economic Opportunity
? Housing
? Public Health
? Transportation
? Flooding
? Environment
? Governance and Customer Service


Prior Court Action (if any):
08/18/2018; PGAL Inc.; Study and Design agreement on court
02/09/2021; Sunbelt Water and Sewer relocation agreement on court
03/09/2021; Project Study Report on court