To: Harris County Commissioners Court
Through: Russell A. Poppe, P.E. Executive Director, Harris County Flood Control District
prepared
Prepared By: Matthew K. Zeve, P.E. Deputy Executive Director, Harris County Flood Control District
Subject: Agreement with San Jacinto River Authority, City of Humble, Texas, The Woodlands Municipal Utility District No. 1, Montgomery County Municipal Utility District No. 7, Montgomery County Municipal Utility District No. 46, Montgomery County Municipal Utility District No. 60, and Harris-Montgomery Counties Municipal Utility District No. 386
end
Project ID (If applicable]: J100-00-00-P003
Purpose and Request:
title
Recommendation to execute an interlocal agreement with the San Jacinto River Authority; City of Humble, Texas; The Woodlands Municipal Utility District No. 1; Montgomery County Municipal Utility District No. 7; Montgomery County Municipal Utility District No. 46, of Montgomery County, Texas; Montgomery County Municipal Utility District No. 60, of Montgomery County, Texas; and Harris-Montgomery Counties Municipal Utility District No. 386 for a partnership project in support of a feasibility study and conceptual design on the Spring Creek Watershed Flood Control Reservoirs. (Spring Creek Watershed, Bond ID C-118, Project ID J100-00-00-P003, Agreement No. 2021-137, Precincts 3 and 4).
end
Background and Discussion:
The feasibility study and conceptual design effort would focus on two potential reservoir locations within the Spring Creek watershed. This project is proposed as a continuation of the Spring Creek Siting Study, which is currently being completed as a sub-task to the San Jacinto Regional Watershed Master Drainage Plan project being performed by the Flood Control District and supported by the San Jacinto River Authority (SJRA) and other regional partners. The SJRA received a grant from the Texas Water Development Board's Flood Infrastructure Fund for $1,000,000 with a required local match ...