Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Public Necessity
Project ID (if applicable): E500-24-00-E001
Vendor/Entity Legal Name (if applicable): N/A
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to decree that the Harris County Flood Control District project serve a public purpose and public necessity requires that the Harris County Real Property Division be directed to acquire one fee simple tract for the public project known as Construction of Stormwater Detention Basin at White Oak Bayou and Woodland Trails, for the purpose of stormwater detention. (White Oak Bayou Watershed, Bond ID C-16, Project ID E500-24-00-E001, Precinct 1).
end
Background and Discussion:
The purpose of this project is to reduce the risk of flood damage in the White Oak Bayou (HCFCD Unit E100-00-00) watershed, provide water quality features, and provide space for future improvements by others.
Expected Impact:
This project seeks to reduce flood risks and strengthen resiliency in Harris County by alleviating property and
structural damages to the adjacent community.
Alternative Options:
Taking no action would result in continued risk of flooding.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
|
Action Taken |
10/3/2006 |
2.b.4 |
Public Necessity of DR-1606-040 |
|
Location: N/A
Address (if applicable):
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
N/A |
|
FY 23 |
FY 24 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$ |
$ |
$ |
Total Incremental Expenditures |
$ |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: May 16, 2023
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District
Attachments (if applicable): Findings and Declarations; Survey Description and Map