File #: 24-2342    Version: 1 Name:
Type: Utility Agreement Status: Agenda Ready
File created: 4/11/2024 In control: Commissioners Court
On agenda: 4/23/2024 Final action:
Title: Request for approval to execute a Service Outlet Location Statement for installation of an electric meter with CenterPoint Energy, LLC and authorize the County Auditor to pay monthly bills for electrical power serving a traffic signal at 19419 1/2 Hufsmith-Kohrville Rd 3, UPIN 15104M23NP03, Precinct 3.
Sponsors: Mony Hossain
Attachments: 1. 24-2342-Utility Agreement - 19419 ½Huffsmith- Kohrville 3 Woodland Shore CPE
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

Project ID (if applicable): 15104M23NP03
Vendor/Entity Legal Name (if applicable): CenterPoint Energy, LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval to execute a Service Outlet Location Statement for installation of an electric meter with CenterPoint Energy, LLC and authorize the County Auditor to pay monthly bills for electrical power serving a traffic signal at 19419 1/2 Hufsmith-Kohrville Rd 3, UPIN 15104M23NP03, Precinct 3.
end

Background and Discussion:
Hufsmith-Kohrville Rd 3 is a road project which includes installing a permanent signal to enhance traffic movement. The service outlet location statement is needed to establish electrical service from CenterPoint Energy to power the traffic signal.

Expected Impact:
Approval of the service outlet location statement will allow CenterPoint Energy to establish electrical service to the permanent traffic signal, which is needed to enhance the operation of the intersection Hufsmith-Kohrville Rd & Woodland Shore Dr.

Alternative Options:
All traffic signals require a power source, which is typically obtained through CenterPoint Energy. Alternative options are to place a generator, which is not reliable, or not installed/remove the traffic from the intersection. Both options pose a public safety concern and will impact the operation and increase delay of the intersection.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service