File #: 24-2306    Version: 1 Name:
Type: Contract - Award Status: Agenda Ready
File created: 4/10/2024 In control: Commissioners Court
On agenda: 4/23/2024 Final action:
Title: Request for approval to execute an agreement with Midtown Engineers, LLC in the amount of $93,412.26 for survey, design, and construction services of a new traffic signal at the intersection of Kuykendahl Road at Cypressdale Drive, UPIN 24035MF35D01, Precinct 3, MWDBE Contracted Goal: 20%.
Attachments: 1. 24-2306-Consultant -upin-24035mf35d01-Traffic Signal - Kuykendahl Rd at Cypressdale Dr - FY22-23 -Midtownn-
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN 24035MF35D01
Vendor/Entity Legal Name (if applicable): Midtown Engineers, LLC

MWDBE Contracted Goal (if applicable): 20%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Midtown Engineers, LLC in the amount of $93,412.26 for survey, design, and construction services of a new traffic signal at the intersection of Kuykendahl Road at Cypressdale Drive, UPIN 24035MF35D01, Precinct 3, MWDBE Contracted Goal: 20%.
end

Background and Discussion:
Traffic signals are installed to improve the operation of an intersection and better facilitate pedestrian activities. A traffic study was conducted at the intersection Kuykendahl Road at Cypressdale Drive, warranting a traffic signal.

Expected Impact:
The installation of the new traffic signal should improve the operation of the intersection.

Alternative Options:
Intersections are evaluated in accordance with the 2011 Texas Manual on Uniform Control Devices (TMUTCD), which takes into consideration traffic volume, crashes, pedestrian activity, and the roadway network. The intersection was evaluated, and a traffic signal was warranted. One alternative option is to install a multi-way stop control at the intersection. However, this is recommended as an interim measure while arrangements are being made for the installation of a traffic signal per the TMUTCD.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
09/19/2023
113
ATN Approved

...

Click here for full text