Harris County Logo
File #: 24-2086    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 4/4/2024 In control: Commissioners Court
On agenda: 4/23/2024 Final action:
Title: Request for approval of a change in contract with J Rivas Construction, LLC in connection with High Meadows and Fairgreen Subdivision Drainage Improvements - 2018, adding three calendar days, Job No. 23/0157-1, UPIN 19102MF17C01, Precinct 2, MWDBE Contracted Goal: 26.00%, MWDBE Current Participation: 75.61%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19102MF17C01 - Job No. 23/0157
Vendor/Entity Legal Name (if applicable): J Rivas Construction, LLC
MWDBE Contracted Goal (if applicable): 26.00%
MWDBE Current Participation (if applicable): 75.61%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with J Rivas Construction, LLC in connection with High Meadows and Fairgreen Subdivision Drainage Improvements - 2018, adding three calendar days, Job No. 23/0157-1, UPIN 19102MF17C01, Precinct 2, MWDBE Contracted Goal: 26.00%, MWDBE Current Participation: 75.61%.
end

Background and Discussion:
The High Meadows and Fairgreen Subdivision Drainage Improvements project site consists of subdivision drainage improvements located High Meadows and Fairgreen subdivisions, located west of John F. Kennedy
Boulevard, east of Russ Drive, north of Aldine Mail Route Road and south of Lauder Road., in east Harris
County; discharging into HCFCD Channel P138-01-01.

The Change in contract request includes new items, additional quantities of existing items and deduction from existing items as noted below for the following:
* Removal and replacement of existing slope paving and swap the proposed 36-inch Corrugated Metal Pipe with 36-inch Reinforced concrete pipe - The latest Harris County Flood Control spec does not allow CMP to pass through concrete slope paving and outfall in the channel. Deducted 61 linear foot from line item #34 - 36-inch corrugated metal pipe, additional quantity for line item #31 by 65 linear foot of 36-inch reinforced concrete pipe, added new line item#86 for removal and replacement of slope paving, deducted line item #73 (well pointing) by 564.29 linear fo...