Harris County Logo
File #: 23-0677    Version: 1 Name:
Type: Utility Agreement Status: Passed
File created: 1/23/2023 In control: Commissioners Court
On agenda: 1/31/2023 Final action: 1/31/2023
Title: Request for approval to execute a Service Outlet Location Statement for the installation of an electric meter with CenterPoint Energy and to authorize the County Auditor to pay monthly bills for 9506 1/2 N Eldridge Pkwy, Houston, TX 77065 (intersection of North Eldridge Pkwy at Fetlock Drive) for electrical power serving a traffic signal, Precinct 3.
Attachments: 1. 23-0677 SOLS- 9506.5 N Eldridge Pkwy.pdf
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

Project ID (if applicable): 23035MF2NK01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval to execute a Service Outlet Location Statement for the installation of an electric meter with CenterPoint Energy and to authorize the County Auditor to pay monthly bills for 9506 1/2 N Eldridge Pkwy, Houston, TX 77065 (intersection of North Eldridge Pkwy at Fetlock Drive) for electrical power serving a traffic signal, Precinct 3.
end

Background and Discussion:
A traffic study was conducted at North Eldridge Pkwy at Fetlock Drive, which warranted a traffic signal at the intersection. The traffic signal will enhance safety as it relates to the intersection operations. The service outlet location statement is needed to establish electrical service from CenterPoint Energy to power the traffic signal.

Expected Impact:
Approval of the service outlet location statement will allow CenterPoint Energy to provide electrical service to the traffic signal, which is needed to enhance the public safety and operation of the intersection of North Eldridge Pkwy at Fetlock Drive.

Alternative Options:
All Traffic Signals require a power source, which is typically obtained through CenterPoint Energy. Alternative options are to place a generator, which is not reliable, or not install the traffic signal at the intersection. Both options pose a public safety concern and will impact the operation and increase delay of the intersection.