Harris County Logo
File #: 23-0664    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/23/2023 In control: Commissioners Court
On agenda: 1/31/2023 Final action: 1/31/2023
Title: Request for approval of a change in contract with D & W Contractors Inc. in connection with Storm Sewer Installation and Maintenance at Various Locations for Harris County Precinct 2 - 21/0223 for the Recovery and Resiliency Division, adding 25 calendar days, with an addition in the amount of $115,066.61, Job No. 21/0223-4, UPIN 22208MF2ES01, Precinct 2, MWDBE Contracted Goal 11%, MWDBE Current Participation 8.5%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 21/0223 - UPIN 22208MF2ES01
Vendor/Entity Legal Name (if applicable): D & W Contractors, Inc.

MWDBE Contracted Goal (if applicable): 11.00%
MWDBE Current Participation (if applicable): 8.5%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with D & W Contractors Inc. in connection with Storm Sewer Installation and Maintenance at Various Locations for Harris County Precinct 2 - 21/0223 for the Recovery and Resiliency Division, adding 25 calendar days, with an addition in the amount of $115,066.61, Job No. 21/0223-4, UPIN 22208MF2ES01, Precinct 2, MWDBE Contracted Goal 11%, MWDBE Current Participation 8.5%.
end

Background and Discussion:
The Recovery and Resiliency Division project includes the construction of Storm Sewer Installation and Maintenance at Various Locations for Harris County Precinct 2. The Contract was approved in Commissioners Court on October 12, 2021. The location of the work is in the Eastex Freeway Forest Subdivision Sections 3 & 4 in the Halls Bayou Watershed. The proposed improvements include storm sewer, waterline, roadway paving, driveway paving, roadside ditches and improvements to an existing outfall. Changes include additional quantities for roadway construction that were underestimated and reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes. Waterline items will be reimbursed by Water Control and Improvement District 74 in the final accounting of the project.
The Change in contract request includes new items for the following:
* PCO 16 - New 12" x 8" Waterline Tee - Added new Item "12"x8" Waterline Tee Connection" ...

Click here for full text