Title: Request for approval to execute an amendment with Isani Consultants, L.P. in the amount of $53,055.00 for Professional Engineering Services to provide improvements to Stuebner Airline Road Segment C - from 700 feet south of FM 2920 to 500 feet west of Leitner Way Drive - 2018, UPIN 18104MF0WT01, Precinct 3, (project was awarded prior to launch of County's M/WBE Program).
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 18104MF0WT01
Vendor/Entity Legal Name (if applicable): Isani Consultants, L.P.

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval to execute an amendment with Isani Consultants, L.P. in the amount of $53,055.00 for Professional Engineering Services to provide improvements to Stuebner Airline Road Segment C - from 700 feet south of FM 2920 to 500 feet west of Leitner Way Drive - 2018, UPIN 18104MF0WT01, Precinct 3, (project was awarded prior to launch of County's M/WBE Program).
end

Background and Discussion:
The County engaged Isani Consultants, L.P. to amend their existing contract and provide additional professional engineering services for the design of a stormwater pump station and related site electrical design for the subject project.

Expected Impact:
The addition of the stormwater pump station design will give the County the option of using pumped detention to minimize the footprint impact of the detention pond while still providing adequate mitigation for the roadway improvements.

Alternative Options:
An alternative would be to not add stormwater pump station design, which would limit the detention to gravity only and likely result in a detention facility with a larger footprint and additional property acquisition.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
February 27, 2018
1.f.3
Recommendation for authorization to negotia...

Click here for full text