File #: 23-0561    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/19/2023 In control: Commissioners Court
On agenda: 1/31/2023 Final action: 1/31/2023
Title: Request for approval of a fourth contract amendment to an agreement with Lone Star Housing and Community Development Corporation and Granada Terrace Apartments, LP, to extend the construction completion period to June 30, 2023 for the Granada Terrace Apartments project.
Attachments: 1. 22GEN4420_Granada Terraace_4th Amendment_v2
Department: Community Services
Department Head/Elected Official: Thao Costis, Interim Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): D2017-60
Vendor/Entity Legal Name (if applicable): Granada Terrace Apartments, LP

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval of a fourth contract amendment to an agreement with Lone Star Housing and Community Development Corporation and Granada Terrace Apartments, LP, to extend the construction completion period to June 30, 2023 for the Granada Terrace Apartments project.
end

Background and Discussion:
On May 19, 2020, Commissioners Court approved an agreement between Harris County, Lone Star Housing and Community Development Corporation, and Granada Terrace Apartments, LP for the Granada Terrace Apartments project. On March 8, 2022, May 24, 2022, and August 23, 2022, Commissioners Court approved the first, second, and third amendments that amended the agreement, respectively.

Attached for Commissioners Court approval is the fourth amendment to the agreement. The parties desire to amend said agreement to extend the 18-month construction completion requirement by an additional six (6) months to June 30, 2023, due to labor issues that prevented substantial completion from occurring by December 2022.

Expected Impact:
The expected impact is to extend the construction contract to allow the timely completion of the project.

Alternative Options:
Alternative option is that the project will not be completed within the contracted timeframe.




Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
X Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda It...