File #: 23-0504    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/19/2023 In control: Commissioners Court
On agenda: 1/31/2023 Final action: 1/31/2023
Title: Request for approval of change in contract No. 1 with Lecon, Inc. for Channel Improvements and Repair, adding 31 calendar days and resulting in an addition of $100,000 to the contract amount. (White Oak Bayou Watershed, Project ID E125-00-00-X007, Job No. 21/0364, Precinct 1, MWDBE Contracted Goal: 14%, MWDBE Current Participation: 18.72%).
Attachments: 1. 013123 CIC LECON PCT 1 backup
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): E125-00-00-X007
Vendor/Entity Legal Name (if applicable): Lecon, Inc.

MWDBE Contracted Goal (if applicable): 14%
MWDBE Current Participation (if applicable): 18.72%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 1 with Lecon, Inc. for Channel Improvements and Repair, adding 31 calendar days and resulting in an addition of $100,000 to the contract amount. (White Oak Bayou Watershed, Project ID E125-00-00-X007, Job No. 21/0364, Precinct 1, MWDBE Contracted Goal: 14%, MWDBE Current Participation: 18.72%).
end

Background and Discussion:
New pay items will be added to the contract and quantities of existing pay items will be increased. During bidding, the imported fill pay item was inadvertently left out, and a quote had to be obtained from the Contractor for inclusion by change order. The Engineer of Record made revisions which resulted in an increase in the boulders and rock needed for armoring the slopes, an increased number of trees cleared as erosion encroached on root zones, and an increase in the excavation quantities to match revised design slopes and remove highly erodible sand along the toe of slope.

Expected Impact:
This RCA is required to complete the HCFCD construction contract under the original or needed revised scope.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.