Harris County Logo
File #: 23-0491    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/19/2023 In control: Commissioners Court
On agenda: 1/31/2023 Final action: 1/31/2023
Title: Request for approval of amendment No. 2 to agreement with Lockwood, Andrews & Newnam, Inc., in the amount of $150,000, for additional engineering services in support of the Lauder Stormwater Detention Basin Phase II, HCFCD Unit P500-06-00. (Greens Bayou Watershed, Bond ID C-34, Project ID P500-06-00-E006, Agreement No. 2020-60, Precinct 2, MWDBE Contracted Goal: 29%, MWDBE Current Participation: 29%).
Attachments: 1. 013123 AGMT LAN 2020-60 PCT 2 backup
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): P500-06-00-E006
Vendor/Entity Legal Name (if applicable): Lockwood, Andrews & Newnam, Inc.

MWDBE Contracted Goal (if applicable): 29%
MWDBE Current Participation (if applicable): 29%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of amendment No. 2 to agreement with Lockwood, Andrews & Newnam, Inc., in the amount of $150,000, for additional engineering services in support of the Lauder Stormwater Detention Basin Phase II, HCFCD Unit P500-06-00. (Greens Bayou Watershed, Bond ID C-34, Project ID P500-06-00-E006, Agreement No. 2020-60, Precinct 2, MWDBE Contracted Goal: 29%, MWDBE Current Participation: 29%).
end

Background and Discussion:
The Lauder Stormwater Detention Basin was increased in size to provide a larger stormwater detention basin capacity by increasing the total excavation volume from 526,900 cubic yards to 1,164,400 cubic yards once additional funding was available. This increase results in the estimated construction period from 306 days to 582 days. This increase also requires additional engineering services needed for a larger project. This project scores in the 1st quartile under the 2022 Prioritization Framework approved by Commissioners Court.

Expected Impact:
The increase in total volume of the stormwater detention basin capacity will reduce the frequency of flooding and future flood damages to homeowners.

Alternative Options:
There are no viable alternatives to this item being requested.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Act...