Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): E125-00-00-X007
Vendor/Entity Legal Name (if applicable): iGET Services LLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval of amendment No. 2 to an agreement with iGET Services LLC, in the amount of $75,000, to provide additional construction phase engineering services in support of channel improvements and repairs on HCFCD Unit E125-00-00. (White Oak Bayou Watershed, Project ID E125-00-00-X007, Agreement No. 2018-62, Precinct 1, MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program).
end
Background and Discussion:
Construction Phase Services are required from the design consultant during the construction process. Changes have occurred to the channel since the original survey. Because of this, design input for the impacted areas is required. This amount of change was not anticipated when the original construction phase services effort was estimated.
Expected Impact:
Construction phase services will allow the engineer of record to provide responses to requests for information from the contractor, review submittals, and update to drawings to complete the project within schedule.
Alternative Options:
Select a different consultant to perform construction phase services requirements.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
9/26/2017
I.2.b.2
ATN
5/1/2018
I.2.a.9
Agreement
2/11/2020
I.2....
Click here for full text