File #: 22-5984    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/20/2022 In control: Commissioners Court
On agenda: 9/27/2022 Final action: 9/27/2022
Title: Request for approval of a change in contract with WadeCon, LLC in connection with Westgate U/R Subdivision Drainage Improvements - 2018, adding 10 calendar days, with an addition in the amount of $13,600.00 for temporary driveways in connection to Job No. 21/0423-1, UPIN 19103MF14901, Precinct 3, MWDBE Contracted Goal 28%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19103MF14901 / Job No. 21/0423
Vendor/Entity Legal Name (if applicable): WadeCon, LLC

MWDBE Contracted Goal (if applicable): 28%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with WadeCon, LLC in connection with Westgate U/R Subdivision Drainage Improvements - 2018, adding 10 calendar days, with an addition in the amount of $13,600.00 for temporary driveways in connection to Job No. 21/0423-1, UPIN 19103MF14901, Precinct 3, MWDBE Contracted Goal 28%.
end

Background and Discussion:
Westgate Subdivision Drainage Improvements project is located in Northwest Harris County, approximately 2.5 miles from Highway US-290 north of Cypress North Houston Road, east of N. Eldridge Parkway, and west of Huffmester Road. The scope of this project is to regrade approximately 12,850 linear feet of existing roadside ditches, upsize culverts, replace driveways, and replace the existing roadway throughout the subdivision to the Harris County standard width and depth. Changes approved by the Engineer of Record provides temporary driveways to accommodate the residents need to park their vehicles during construction. New Item include "Temporary Driveway" - $13,600.00, add 10 days.


Expected Impact:
This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This change in contract is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the Westgate subdivision...

Click here for full text