Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E. PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN 23104MF2KRO1
Vendor/Entity Legal Name (if applicable): CenterPoint Energy Houston Electric, LLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a Facilities Extension Agreement with CenterPoint Energy Houston Electric, LLC and to authorize the County Auditor to approve a Purchase Order for $13,884.00 for the cost associated with changing service from Primary Metered to Major Underground facilities in connection with the Hockley Service Center at 28511 Old Washington Road, Hockley, TX 77447, UPIN 23104MF2KRO1, Precinct 4.
end
Background and Discussion: CenterPoint requires signed Facilities Extension Agreement for easement request
for new service.
Expected Impact:
If this agreement is not moved forward the project it supports cannot begin.
Alternative Options:
There are no alternate options as CenterPoint is the one and only entity we can deal with in these matters.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
X Governance and Customer Service
Prior Court Action (if any): N/A
Date
Agenda Item #
Action Taken
Location:
Address (if applicable): 28511 Old Washington Road Hockley, Tx 77447
Precinct(s): Precinct 4
Fiscal and Personnel Summary
Service Name
SFY 22
FY 23
Next 3 FYs
Incremental Expenditures (do NOT write values in thousands or millions)
Labor Expenditures
$
$
$
Non-Labor Expenditures
$13,884.00
$
$
Total Incremental Expenditures
$13,884.00
$
$
Funding Sources (do NOT write values in thousands or millions)
Existing Budget $13,8...