Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 20/0271
Vendor/Entity Legal Name (if applicable): Mar-Con Services, LLC
MWDBE Contracted Goal (if applicable): 0%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Mar-Con Services, LLC in connection with Cypress Rose Hill Road 11 - 500ft north of Seidel Cemetery Rd to 800ft north of Tomball-Waller Road, adding 3 calendar days, with an addition in the amount of $7,827.00, Job No. 20/0271-3, UPIN 161033001518, Precinct 4, MWDBE Contracted Goal: 0% (project was awarded prior to launch of County's M/WBE Program).
end
Background and Discussion:
Project includes construction of Cypress Rose Hill Road 11 - 500ft north of Seidel Cemetery Rd to 800ft north of Tomball-Waller Road. Change includes time and cost for installation of new electrical service pole (3 days, $7,827.00).
Expected Impact:
Changes allow additional work needed to complete the project within the original scope and in accordance with Precinct requirements. Additional time allows the Contractor to complete additional work without penalty.
Alternative Options:
Reduce the scope of the project to eliminate the need for additional work.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
11/10/2020
21.d.8.i
Contract Award
10/12/2021
41
Contract Amendment for additional funds and extension of project term
03/08/2022
40
Contract Amendment for additional funds and extension of project term
...
Click here for full text